Schedule a test

NeoLoad allows you to schedule a test at a specified time.

  1. Select the scenario to be run.
  2. Click on the Advanced button.
  3. Select the Schedule a test tab.
  4. Check the Enable scheduling for this scenario check box.
  5. Select a date and time.
  6. Enter a repeat rule (optional).
  7. Schedule the test in debug mode (optional). See Start a test for more information.
  8. Send to NeoLoad Web the data related to the test (optional).
  9. Enter a test description (optional).
  10. Click OK.